Power development in Sauda | |
| 28.04.2005: The board of directors of Orkla ASA approved on 27 April Elkem's decision to implement the hydropower development at AS Saudefaldene. | |
Costed at NOK 1 640 million, this project involves upgrading older generating plant - partly in order to meet official demands for phasing out forge-welded pipes.
Development work involves establishing roughly 500 GWh in new generating capacity. Construction is due to start in May 2005, with completion scheduled during 2008. Enclosed pdf file | |
| Ref.:
Svein Sundsbø, Chairman of the Board of Directors AS Saudefaldene, Tel: + 47 90954717 Ole Kristian Lunde, SVP Corporate Communications, Tel: + 47 22544431 | |
Date: 28. apr 2005 Kl 11.04 | |